Cloudutsuk Platform: Deployment and Go-Live
How the platform's foundation went live on 2026-10-11, how it's deployed and rolled back, and what the MVP launch in Phase 3 needs.
There’s no launch day for a platform that only I use, and that’s exactly why I wanted a go-live discipline anyway: on 2026-10-11 the foundation (four clusters, secrets, DNS, sign-in, GitOps, remote access and backups) became something other phases build on, and from then on breaking it costs real work. This post records how Phase 0 was signed off, how things get deployed and rolled back, and what the MVP launch in Phase 3 still needs.
Production readiness review
Each phase ends with a readiness review: its steps’ Done when checks, re-run against the live system rather than taken from memory. Phase 0’s ran on 2026-10-11:
| Check | Result |
|---|---|
core, mon, platform and ai exist and are Ready | Pass |
| Every ClusterSecretStore is Valid; every ExternalSecret synced (23 across four clusters) | Pass |
A cluster can’t read another cluster’s secrets (mon on core/*) | Pass (403) |
Internal names resolve on the DGX and from pods in mon, platform and ai; HTTPS with a valid certificate | Pass |
| Argo CD: every app Synced and Healthy (11) | Pass |
Sign-in through Keycloak with Entra ID: kubectl on mon, OpenBao | Pass |
| My phone on mobile data reaches the internal UIs over Tailscale | Pass |
| Velero’s storage location Available in all three clusters; first backups Completed | Pass |
The blog still answers on https://cloudutsuk.com after the DNS move | Pass |
| Reboot brings everything back unsealed | Deferred |
Sign-in with Google; kubectl from the laptop; another tailnet user denied | Deferred |
Deferred checks aren’t failures, but they’re written down with a reason in the Phase 0 steps, so they don’t quietly turn into “done”.
Phase 1’s ran on 2026-10-13. Its milestone, M1, is one sentence: a commit to a hello-world service ends with an Argo CD app Synced and Healthy on the new SHA.
| Check | Result |
|---|---|
| M1: a commit to hello-world ends Synced and Healthy on its SHA, smoke test passing | Pass: pushed 21:44:27 UTC, digest committed 1 min 45 s later, Healthy and serving that SHA at 8 min 25 s |
| A failing unit test stops the run before the image is built | Pass (throwaway PR: test failed in 13 s, image job skipped) |
| A commit that breaks the security gates builds nothing | Pass (2026-10-12: six gates blocked it) |
main images are signed and SBOM-attested; Kyverno admits them and refuses unsigned ones | Pass (dry runs on all three clusters) |
All seven Kyverno policies deny on platform, mon and ai; no failing reports | Pass (0 failures, four written exceptions) |
A job runs on the homelab runners under Deny | Pass |
A job runs on the homelab-iac runners | Pass on 2026-10-12; since step 5a only a dry run of its pod (admitted) |
| A failing smoke test fails the sync, and a revert recovers | Pass (2026-10-12, step 6) |
| Argo CD: every app Synced and Healthy (45) | 44 of 45: monitoring-base is Degraded because its Alertmanager secret was never seeded in OpenBao (Phase 2, not a Phase 1 regression) |
The details of the pipeline are in CI/CD and Release Management.
Go-live checklist
The real go-live is the MVP at the end of Phase 3, when the portal and labs are usable (MVP definition). The checklist I’d hold it to:
- Every Phase 1 to 3 step shows Done with its date, and the deferred Phase 0 checks are closed or explicitly accepted.
- The portal signs in through Keycloak only; no local accounts are left enabled.
- The reboot test passes with the portal and lab runner in place.
- A restore of last night’s backup works: Keycloak’s realm and an OpenBao secret come back in a throwaway cluster.
- Alerts reach me: the heartbeat, and from Phase 2 the
monalerts for backups, certificates, sealed OpenBao and Argo CD drift. - Deploying a lab beyond the memory budget is refused with a clear message.
- The playbook posts describe what’s running, with no stale TODO callouts for things that now exist.
TODO: Will anyone besides me use the portal at MVP? If so, the checklist needs their accounts in Keycloak’s
viewersgroup and a short how-to for them.
Deployment runbook
There are exactly two ways anything reaches a cluster, and the runbook is which one applies:
| What | Path | Rollout |
|---|---|---|
| Clusters, and what must exist before Argo CD (OpenBao, Keycloak, Zot, Velero and the like) | infra-local, Terragrunt | Plan, read it, apply |
| Everything else: apps, monitoring, the AI stack | A commit to homelab-gitops | Argo CD syncs within three minutes |
For a bootstrap release, the steps are:
1
2
3
4
5
6
7
# 1. plan, and read it: "update in-place" is fine; "must be replaced" on a cluster means a rebuild
venv/bin/python entrypoint.py --cloud k3d --environment homelab --provider helm \
--stack platform --resource velero-ui --terragrunt plan
# 2. apply
venv/bin/python entrypoint.py ... --terragrunt apply
# 3. verify: pods Ready, ExternalSecrets synced, the endpoint answers
kubectl --context k3d-platform -n velero-ui get pods,externalsecret,certificate
Two rules from Phase 0 belong in every deploy. Restart a k3d node only with k3d cluster stop/start, never docker restart, which drops the host aliases (lesson L026). And a chart whose objects use its own CRDs is split into two releases, the second applied after the first (lesson L030).
Data migration plan
Phase 0 had one real migration: moving cloudutsuk.com’s DNS from GoDaddy to Cloudflare. Every record was exported first, compared with dig after the move, and the old zone was left in place for a week as a fallback. The blog never went down.
The migrations still ahead are small and planned in their phases:
- Labs to contract v2 (Phase 2): the two existing labs join the
homelabnetwork and send telemetry tomoninstead of bundling their own Grafana stack. Their posts’ setup steps change with them. - The old
otel-democluster retires when its lab moves. - Inventory history (Phase 4) starts empty; there’s no older cost data to bring in.
There’s no user data to migrate. Keycloak’s realm and OpenBao’s secrets were created fresh, and the Velero backups are what would move them if the DGX were ever replaced.
Smoke tests
Today’s smoke tests are the checks in the readiness review, run by hand after a change. They’re cheap and they caught real problems: the first mon secret store was checked before CoreDNS had loaded its forwarding (lesson L022).
Three are already automated:
- The boot unit checks after every boot that
coreis up, OpenBao unsealed and Tailscale routing. - The heartbeat checks OpenBao’s health every five minutes.
- Velero checks its storage location every minute.
Phase 1 adds the real pattern: an Argo CD PostSync job per app that calls the app’s health and one real request, and marks the sync failed if they don’t answer (Phase 1 steps).
Monitoring and alert validation
Until mon has its LGTM stack (Phase 2), the only alert is the heartbeat, and it covers the failure that matters most at this stage: the DGX going silent. It pings healthchecks.io every five minutes while OpenBao answers healthy, and pings the check’s failure URL with the reason when it doesn’t, so a sealed OpenBao emails me as fast as a power cut does.
An alert that has never fired is a guess, so each one gets validated once:
- Heartbeat: I’ll stop the timer for 15 minutes and expect the email.
- From Phase 2: each mixin alert and each platform rule (backups older than 26 hours, sealed OpenBao, certificate expiry, Argo CD out of sync) gets fired once on purpose, and the Watchdog alert proves the alert pipeline itself is alive.
TODO: Run the heartbeat test (stop
homelab-heartbeat.timer, wait for the email, start it again) and note the delay you saw.
Support team readiness
The support team is me, so readiness means being able to fix things at 11 pm without remembering how they were built. That’s covered by:
- Runbooks in the repos:
infra-local’s README and eachhost/folder’s README (OpenBao, DNS, network, boot, heartbeat, backups). - The why: the ADR log and the lessons learned.
- A local view that needs no sign-in: Headlamp and Popeye on the DGX, plus a link page of every route and the external services (Tailscale, Cloudflare, healthchecks.io, Azure).
- Break-glass when Keycloak or
coreis down: SSH to the DGX, over the tailnet or the home network; the local admin accounts sealed in the offline kit.
The SRE agent (Phase 6) will take the first look at alerts, but it only proposes fixes; I still approve them.
User and stakeholder communications
The audience is readers of this blog, so the communication channel is this playbook. Every phase ends by updating the posts with what was actually built, ticking the roadmap and moving the project card’s status, which is what this post is part of. Phase 0’s foundation moved the card from Planning to In progress on 2026-10-11.
Decisions are published as ADRs and problems as lessons, so a reader can follow not just what was built but why, and what went wrong on the way. Nothing private goes out: no IDs, keys, tailnet names or private repo links (the ADR and lessons scripts check for them).
Cutover and rollback plan
Rollback depends on which deployment path the change took:
| Change | Rollback |
|---|---|
An app in homelab-gitops | git revert the commit; Argo CD syncs the previous state |
| A bootstrap release | Re-apply the previous values from git (helm rollback only as an emergency, then fix git) |
| A cluster setting that rebuilds the cluster | Rebuild from the previous resources.yaml; host-path data survives, then re-apply its releases |
| Lost or corrupted data | Velero restore of the dumps, then pg_restore or bao operator raft snapshot restore |
| DNS | Cloudflare keeps the zone history; the GoDaddy zone was the fallback during the move |
The worst case is losing the DGX’s disk. The plan: new hardware, infra-local rebuilds the clusters from git and remote state, the offline kit unseals OpenBao, and Velero brings back last night’s dumps. That path is only a plan until the first restore test has run.
Launch decision and sign-off
I make the call, against written criteria rather than a feeling: a phase is signed off when every one of its steps shows Done with a date, or Deferred with a reason, and its readiness review has been re-run on the live system. Phase 0 was signed off that way on 2026-10-11, with five deferred items (the reboot test, the two laptop tests over Tailscale, Google sign-in, and core’s own Keycloak sign-in, which waits for its next rebuild).
The MVP launch at the end of Phase 3 uses the same rule plus the go-live checklist, and it doesn’t happen with an open item from the “worst case” path: no restore test, no launch.
Checklist
- Phase 0 readiness review run on the live system and recorded (2026-10-11)
- Card moved to In progress; roadmap and Phase 0 steps updated
- Heartbeat alert fired once on purpose
- Reboot test passed
- First restore test of
core’s backup into a throwaway cluster - PostSync smoke tests on every app (Phase 1)
- Every Phase 2 alert fired once on purpose
MVP go-live checklist passed and signed off (Phase 3)